CLIENT

PROJECT

LOCATION

DURATION

ISG

Wellington House AIB Removal

Wimbledon

4 Weeks

Project Overview:

Refurbishment of ground floor retail spaces and existing office above with the addition of a one storey roof extension and rear infill to create an uplift of 1800 sqm, doubling the existing area. The windows frames, panels and stairwell structure to the roof of the dated façade at Wellington House in Wimbledon needed to be removed and replaced with contemporary, patterned brickwork.

Alltasks in-house design team produced a structure that provided all trades access and a safe working environment for our asbestos removal team to remove the existing AIB panels. The scaffold structure designed with bridging beams to encapsulate the façade provided a safe working environment for all trades whilst simultaneously maintaining access to the retail businesses at street level.

Back to all

Case Studies

© 2019 Alltask Ltd. Registered in England and Wales.

Company No. 02689988 VAT Registration No. 573 8265 11

Date of Incorporation: 21 February 1992

  • Facebook Social Icon
  • Instagram Social Icon
  • LinkedIn Social Icon