Project Overview:
Alltask provided labour to install access to new build EFW GASS shoring system using client owned scaffolding for concrete pours to the five storey tipping hall in addition to our own system scaffold. Working in collaboration with the main contractor and other on-site teams we proposed cost and program reductions satisfying SLAs and KPIs.
Alltask provided access to walkways adjacent to excavations and safety routes during enabling works, beyond mandatory requirements. Alltasks in-house design team successfully proposed V.E. option for 3no HAKI staircases 20m - 60m levels on varying zones. We utilised the DOKA staircase system scaffold to provide access within the shafts.