Tooting Station Completion

Site Access Bridge Rail Division

Tooting Station's week 5 abnormal possession was a success for our Rail Division and our valued client BAM Nuttall Ltd. We installed a 10kn/m2 site access bridge complete with 1000kg lifting frames to assist our client with their upcoming AFA scheme, which is programmed to start in the coming weeks.

Additionally, each pedestrian platform now boasts 55Lm of scaffold hoarding, all expertly designed by our external design partners Prime Scaffold and Structural Designs Ltd (PSD). Well done to the entire team who dedicated their bank holiday weekend, completing all the work in just the one single weekend possession, over the course of 6 separate shifts, with a total of 72-man shifts worked.

Access Bridge Tooting Station
Tooting Station Access Bridge

Well done to everyone involved!

Service: Scaffolding Projects