Kemsley Paper Mill

Scaffolding and Insulation Maintenance Contract

Scaffold and Insulation Maintenance Contract

Kemsley Mill has an annual production capacity of around 800,000 tonnes and is the second biggest recovered fiber-based paper operation in Europe. DS Smith invested over £100m to purchase and rebuild PM6 to make lightweight corrugated case material (CCM). Kemsley Mill produces Light Medium, the first recycled lightweight paper manufactured in the UK. Alltask provides an ongoing maintenance contract, offering Scaffold & Insulation services 24 hours a day, 7 days a week, 365 days a year.

The contract involves one planned shutdown per week involving up to 15 operatives outside of the shutdowns. Alltask supports the ongoing needs of the mill on a day-to-day basis with a fluctuating labour force ranging from four to eight operatives. All operatives hold a CCNSG Safety Passport & are Confined Space trained. Alltask also supports the mill with an ‘out of hours’ call-out system with a guaranteed response time of 2 hours. All scaffolds are erected to a bespoke design or TG20 compliance sheet.

 

Scaffold and Insulation Maintenance Contract
Scaffold and Insulation Maintenance Contract

"As another project is coming to the end for me, I wanted to let you know, your team here at K4 have again excelled, nothing was too much trouble and advice was always freely given.  Another great job by Alltask"

Service: Scaffolding Projects